Masonry Magazine December 1979 Page. 31

Masonry Magazine January 1979 Page.31

Masonry Magazine January 1979 Page.31
A 37,000 sq. ft. warehouse, once used to house railroad freight cars on Baltimore's south side, served as a marshalling facility for the prefabricated panels. On an assembly line, panels were hauled by cable and carried on a 100-ft. overhead crane through each production stop.

First, welders attached relief angles and other metal accessories to the light gauge panels. Next, workers covered panel exteriors with a layer of gypsum sheathing, which was later coated with waterproof polyethylene vapor barrier. Brick ties, added later, allow the masonry to flex slightly without cracking. At the final stop, masons employed by Smoot applied brickwork to the rows of neatly arranged panels.

Completed panels, each weighing an average of 15,000 pounds, were then hauled outside, stored and sequenced while braced in steel carriages. The panels' size averages 12 ft. high by 17 ft., but varies in width from 10-24 ft. Because of extreme size and weight, the largest panels were bricked at the jobsite.

After delivery to the construction site, panels were fitted with handling brackets, lifted from the trailers in pre-planned sequence, and hoisted into position with the erector's 150-ton mobile "DEMAG" tower crane. Workers stationed on upper floors received each panel, placing it against the steel in-system boundary.

Prefabrication saved considerable time, money and manpower. Henry lauded the "swift, efficient erection process" as a direct result of using brick panels framed with light gauge steel studs. "By using a prefabrication shop, shipping panels to the site, and using cranes to lift the panels into place, the job went unbelievably fast," said Henry, who also pointed out that a ten-member on-site crew erected an average of 10 panels per day, but often installed as many as 20 per day.

Welch cited the cost savings and outstanding quality achieved with this breakthrough in highrise masonry and steel construction. "This unique loadbearing exterior wall system not only reduced construction costs by 10 percent, but will provide a significant savings in future operation and maintenance," he said.

The new building serves as a fitting tribute to the team of experts whose efforts to overcome various construction challenges resulted in a bold new concept in construction technology.


MASONRY INFORMATION
AVAILABLE FREE OF CHARGE

The primary purpose of the International Masonry Institute (IMI) is to provide useful information about masonry design and construction to architects, engineers, owners, investors, government agencies and builder-developers as well as mason contractors, craftsmen and others.

If you would like a free catalog listing IMI publications, free loan films and slide shows, and recommended information from other national masonry associations, contact: IMI, 823 Fifteenth St., N.W., Washington, D.C. 20005, telephone: 212/783-3908. Mention you saw this announcement in MASONRY.

Steel cables were installed as temporary fasteners to hold the panels in place as welders attached graphite-lubricated connection assemblies. Specially designed sliding connection assemblies, installed between the panel and in-system, allowed for the slight vertical movement which occurs as live loads are applied to the structural steel framework. Finally, panel joints were filled and caulked.

Steel cables were then installed as temporary fasteners to hold the panels in place as welders attached graphite-lubricated connection assemblies. Specially designed sliding connection assemblies, installed between the panel and in-system, allowed for the slight vertical movement which occurs as live loads are applied to the structural steel framework. Finally, panel joints were filled and caulked.

Sharing responsibility for on-the-job quality assurance were Korda, Nemeth, Kadakia and Jezerinac, Ltd., Columbus, Ohio, and A. J. Julicher & Associates, Potomac, Md. Project manager and vice president of the Smoot Co., Arthur K. Welch, and architect Robert Henry agreed that


ORIGINATORS OF
Pre-Fabricated Glass Block Panels

CUSTOM MADE TO YOUR REQUIREMENTS
NATIONAL DISTRIBUTOR
SCHALKE GLASS BLOCK - GERRIX HOLLOW
GLASS BLOCK

MANY STYLES AND SHAPES

SASH REPLACEMENT

SPECIALISTS IN THE INSTALLATION OF
GLASS BLOCK

FRED BEYER
7810 S. Claremont Chicago, III. 60620
(312) PR 8-4300

MASONRY/NOVEMBER DECEMBER, 1979 31


Masonry Magazine December 2012 Page. 45
December 2012

WORLD OF CONCRETE

REGISTER NOW; RECEIVE A FREE HAT!
The first 25 people to register this month using source code MCAA will receive a free MCAA Max Hat (valued at $15.00)! The MCAA Max Hat features a 3D MCAA logo embroidered on front with a

Masonry Magazine December 2012 Page. 46
December 2012

Index to Advertisers

AIRPLACO EQUIPMENT
888.349.2950
www.airplace.com
RS #296

KRANDO METAL PRODUCTS, INC.
610.543.4311
www.krando.com
RS #191

REECHCRAFT
888.600.6060
www.reechcraft.com
RS #3

Masonry Magazine December 2012 Page. 47
December 2012

AMERIMIX
MORTARS GROUTS STUCCOS

Why Amerimix Preblended Products?

576

The choice is CLEAR:

Consistency

Labor reduction

Enhanced productivity

ASTM - pretested to ASTM specifications

Masonry Magazine December 2012 Page. 48
December 2012

MASON MIX
Type S Mortar
QUIKRETE
www.quikrete.com
800-282-5828

MASON MIX
Type 5 Mortar
COMMERCIAL GRADE
QUIKRETE

Our mortar mix on Vail's Solaris was so consistent, every bag was like the next. And the next