Masonry Magazine October 1983 Page. 13

Masonry Magazine October 1983 Page. 13

Masonry Magazine October 1983 Page. 13
Unit Masonry Wall Wins Over Competitive Materials

Chicago apartment highrise topped out in record time

When the architect, general contractor and owners of the 30-story, 280-unit Clark & Chestnut Apartments on Chicago's Near North Side were engaged in pre-construction planning, they had to decide which of several alternative exterior wall treatments to utilize.

They looked at and rejected-metal panels, aluminum curtain walls, precast concrete panels, poured-in-place concrete. Instead, they selected a unit masonry wall as the most cost and energy-efficient system. They also opted for the warmth and color the brick wall would add to the builder.

Record Topping-out Time

The superstructure was completed in record time-from caissons through topping-out required less than five months. The actual pour cycle was calculated at three days, or two floors per week. Thus it required only 15 weeks to top out the 30-story structure, considered to be a record for this type of construction.

According to William V. Nagy, vice president of the general contracting firm, E. W. Corrigan Construction Co., Oak Brook, III., "The much talked about, but illusive, three-day pour-cycle was achieved on this project. The field operation was scheduled to the fraction of an hour."

The masonry work on the Clark Chestnut Apartments, supplied by Hansen & Hempel, Inc., Elmhurst, W., followed 10 floors behind the concrete pour. Enclosed swing stages protected the bricklayers in the winter months. The attached 244-car garage (pictured) is part of the project.

A climbing tower crane hoists materials on the Clark Chestnut Apartments project. The bricklayers worked from swing stages on their upward climb on the 30-story building.

Windy City Blues

Corrigan's project superintendent. Tom Kelly, said, "Everyone knew exactly where to be and what task they were responsible for to accomplish a smooth flow of materials, men and equipment. The only lost time we had was due to high winds which prevented the climbing tower crane from hoisting the necessary materials to keep the job working.

The mason contractor on the project was Hansen & Hempel. Inc., Elmhurst, III. The masonry work followed 10 floors behind the concrete pour. Work was kept on schedule by working from fully enclosed swing stages during the winter months.

The Clark/Chestnut project was designed by Weese, Seegers, Hickey & Weese, Architects Ltd. of Chicago. Eugene Callahan, Sheldon Baskin and Daniel Eptstein is the developer.

MASONRY-SEPTEMBER/OCTOBER, 1983 13


Masonry Magazine December 2012 Page. 45
December 2012

WORLD OF CONCRETE

REGISTER NOW; RECEIVE A FREE HAT!
The first 25 people to register this month using source code MCAA will receive a free MCAA Max Hat (valued at $15.00)! The MCAA Max Hat features a 3D MCAA logo embroidered on front with a

Masonry Magazine December 2012 Page. 46
December 2012

Index to Advertisers

AIRPLACO EQUIPMENT
888.349.2950
www.airplace.com
RS #296

KRANDO METAL PRODUCTS, INC.
610.543.4311
www.krando.com
RS #191

REECHCRAFT
888.600.6060
www.reechcraft.com
RS #3

Masonry Magazine December 2012 Page. 47
December 2012

AMERIMIX
MORTARS GROUTS STUCCOS

Why Amerimix Preblended Products?

576

The choice is CLEAR:

Consistency

Labor reduction

Enhanced productivity

ASTM - pretested to ASTM specifications

Masonry Magazine December 2012 Page. 48
December 2012

MASON MIX
Type S Mortar
QUIKRETE
www.quikrete.com
800-282-5828

MASON MIX
Type 5 Mortar
COMMERCIAL GRADE
QUIKRETE

Our mortar mix on Vail's Solaris was so consistent, every bag was like the next. And the next