Masonry Magazine April 1999 Page. 14

Masonry Magazine April 1999 Page. 14

Masonry Magazine April 1999 Page. 14
Table 2
Specifications for Masonry Structures (ACI 530.1-98) Submittal and Inspection Requirements
LEVEL 1 QUALITY ASSURANCE
MINIMUM TESTS AND SUBMITTALS

Certificates for materials used in masonry construction indicating compliance with Contract Documents
MINIMUM INSPECTION

Verify compliance with the approved submittals
LEVEL 2 QUALITY ASSURANCE
MINIMUM TESTS AND SUBMITTALS

Certificates for materials used in masonry construction indicating compliance with Contract Documents

Verification of f'm prior to construction, except where specifically exempted by the Code
MINIMUM INSPECTION

As masonry construction begins, verify the following are in compliance:

Proportions of site prepared mortar

Construction of mortar joints

Location of reinforcement and connectors

Prior to grouting, verify the following are in compliance:

Grout space is clean

Placement of reinforcement and connectors

Proportions of site prepared grout

Construction of mortar joints

Grout placement is in compliance

Observe preparation of grout specimens, mortar specimens, and/or prisms

Verify compliance with the required inspection provisions of the Contract Documents and the approved submittals
LEVEL 3 QUALITY ASSURANCE
MINIMUM TESTS AND SUBMITTALS

Certificates for materials used in masonry construction indicating compliance with Contract Documents

Verification of f'm

prior to construction

every 5,000 sq. ft. (464.5 m2) during construction

Verification of proportions of materials in mortar and grout delivered to the site
MINIMUM INSPECTION

From the beginning of masonry construction and continuously during construction of masonry, verify the following are in compliance:

Proportions of site mixed mortar and grout

Placing of masonry units and construction of mortar joints

Placement of reinforcement and connectors

Grout space prior to grouting

Placement of grout

Observe preparation of grout specimens, mortar specimens and prisms

Verify compliance with the required inspection provisions of the Contract Documents and the approved submittals

The Code provides minimum quality assurance levels, and the designer may elect to provide higher thresholds of quality assurance in the project specifications.

Hot Weather Construction

Previously, Hot Weather Code requirements of limiting the spreading of mortar beds greater than 4 feet ahead of masonry and placing units within one minute of spreading mortar were imposed when the ambient air temperature exceeded 100°F or 90°F with a wind velocity greater than 8 mph.

The Hot Weather requirements of ACI 530.1-99 are somewhat more comprehensive. The highest threshold is at an ambient air temperature of 115°F or 105°F with a wind velocity greater than 8 mph. The ambient air temperature is defined as the average of high and low temperature prediction by the local weather bureau for the subsequent 24 hour period.

At this higher threshold, the Code requires shading of materials and mixing equipment from direct sunlight, maintaining sand piles in a damp loose condition and preparing equipment to produce mortar and grout below 120°F in preparation for masonry construction.

During construction, the Code provides for liberal use of cool water in mixing mortar and grout and retempering mortar. Ice water may be used, but the ice is not to come into direct contact with the mortar or grout materials. Equipment and mortar boards should be flushed frequently with cool water.

When ambient air temperature is above 100°F or above 90°F with a wind velocity greater than 8 mph, sand piles are to be maintained in a damp loose condition and equipment is to be cool enough so that mortar temperature is below 120°F.

During construction, cool water should be used in mixing mortar and grout and for retempering mortar. Ice water may be used, but the ice is not to come into direct contact with the mortar or grout materials. Equipment and mortar boards should be flushed frequently with cool water.

After construction, when the ambient air temperature is above 100°F, or above 90°F with a wind velocity of greater than 8 mph, newly constructed masonry should be fog sprayed three times a day for three days.


Masonry Magazine December 2012 Page. 45
December 2012

WORLD OF CONCRETE

REGISTER NOW; RECEIVE A FREE HAT!
The first 25 people to register this month using source code MCAA will receive a free MCAA Max Hat (valued at $15.00)! The MCAA Max Hat features a 3D MCAA logo embroidered on front with a

Masonry Magazine December 2012 Page. 46
December 2012

Index to Advertisers

AIRPLACO EQUIPMENT
888.349.2950
www.airplace.com
RS #296

KRANDO METAL PRODUCTS, INC.
610.543.4311
www.krando.com
RS #191

REECHCRAFT
888.600.6060
www.reechcraft.com
RS #3

Masonry Magazine December 2012 Page. 47
December 2012

AMERIMIX
MORTARS GROUTS STUCCOS

Why Amerimix Preblended Products?

576

The choice is CLEAR:

Consistency

Labor reduction

Enhanced productivity

ASTM - pretested to ASTM specifications

Masonry Magazine December 2012 Page. 48
December 2012

MASON MIX
Type S Mortar
QUIKRETE
www.quikrete.com
800-282-5828

MASON MIX
Type 5 Mortar
COMMERCIAL GRADE
QUIKRETE

Our mortar mix on Vail's Solaris was so consistent, every bag was like the next. And the next