Time Management

Dodging Deadly Delays- Handling the Inevitable

Ask a contractor: "What's the most frustrating part of your job," and nine times out of 10, the response will be: dealing with construction delays. Delay is deadly because it invariably requires extra time, extra attention, and extra labor by the contractor to correct the delay- all of which cost time and money.

By Steve Saucerman, Professional Estimator

Interruptions in project schedules are killers-and not just because they create ulcers for the project superintendent. Delays can be deadly because they require the expenditure of three things that are always in short supply: time, effort and personnel. Add those three items up and they total the fourth thing most contractors are light on-money.

Now, spending money's not a bad thing if and when you planned on spending it. Unfortunately, most of the money expended correcting delay is (probably) unaccounted for during estimating-and therefore absorbed as loss.

Delay is a slippery thief-silently and steadily encroaching on the bottom line. Sometimes it's easy to spot, such as stoppage caused by a busted hose on a backhoe. Other times delay isn't so discernable. Perhaps it will manifest itself as an hour lost waiting for a generator to be delivered or a worker chronically showing up late to work.

The Effects of Delay

DELAY AFFECTS A JOB in many different ways. The loss of money through expended man-hours is easy to visualize, but what about the negative impact on morale and productivity? Let's look at an example:

Imagine you're a superintendent overseeing a million-dollar project and you have the enviable daily responsibility of coordinating 16 to 20 different skilled trades (in different unions), scores of workers, and perhaps hundreds of material deliveries for your project. Broken a sweat yet?

Now, let's suppose that every one of the individual skilled-trade people has their own agendas, attitudes and opinions (which they're seldom afraid to share) regarding virtually everything effecting their work.

During the course of a construction project, the interaction between these variable parties can grow to be quite tense and, it might be said, quite enlightening-if you happen to be an anthropologist studying de-evolution of man. Even on a normal day, a typical exchange between an electrician, let's say, and the super may go something like this:

Electrician, "Hey, you! There are a hundred "@-d*#* ("place name of other trade here") guys in my way and there's no g*@-d*#* way I can get any of my g-d*#* pipe in the g@-d*#* ceiling until...."

Super (to himself), "Good grief, I need a drink!"

Our superintendent has certainly got his hands full and this is just a fraction of his duties. Keep in mind that the owner,


Masonry Magazine December 2012 Page. 45
December 2012

WORLD OF CONCRETE

REGISTER NOW; RECEIVE A FREE HAT!
The first 25 people to register this month using source code MCAA will receive a free MCAA Max Hat (valued at $15.00)! The MCAA Max Hat features a 3D MCAA logo embroidered on front with a

Masonry Magazine December 2012 Page. 46
December 2012

Index to Advertisers

AIRPLACO EQUIPMENT
888.349.2950
www.airplace.com
RS #296

KRANDO METAL PRODUCTS, INC.
610.543.4311
www.krando.com
RS #191

REECHCRAFT
888.600.6060
www.reechcraft.com
RS #3

Masonry Magazine December 2012 Page. 47
December 2012

AMERIMIX
MORTARS GROUTS STUCCOS

Why Amerimix Preblended Products?

576

The choice is CLEAR:

Consistency

Labor reduction

Enhanced productivity

ASTM - pretested to ASTM specifications

Masonry Magazine December 2012 Page. 48
December 2012

MASON MIX
Type S Mortar
QUIKRETE
www.quikrete.com
800-282-5828

MASON MIX
Type 5 Mortar
COMMERCIAL GRADE
QUIKRETE

Our mortar mix on Vail's Solaris was so consistent, every bag was like the next. And the next