Full Contact Project Management
A Contractor's Guide to
Surviving Opportunity
Gary Micheloni

Too many contractors do too much extra work for free. The reason? They don't get paid because they don't ask properly. And for today's session, asking properly doesn't just mean saying "please." But, we'll come back to this in a minute.

So, what's all this talk about a "session"? First off, the session is held right here, every month, in the pages of one of your favorite magazines. But this session is unlike any class you've ever taken. It's a coaching session a nuts-and-bolts, meat-and-potatoes kind of a time together. It's like a class, only without all of the fluff. And instead of being your professor, I'll be your coach. Instead of a PowerPoint presentation, you'll get more of a "chalk talk." And at the end of my talk every month, you'll be introduced to a "guest coach" from an all-star team of coaches who will draw up a strategy you can put to use. Not unlike sports, we'll talk offense and defense-both of which are crucial to good project management. And, when appropriate, I'll give you a page for your "playbook." The first one lists 10 things a Project Manager needs to do today. It's free, and you can get it at playbook@fullcontactPM.com.

Today's session began with my proclamation that too many contractors do way too much work for free, and I stand by that statement. But before one of our team members disagrees, answer this question: How much work did you "donate" last year to your clients? If it was zero, that's good. If, however, you are like most contractors, there will be several zeros preceded by a whole number, and that's not so good.

Because this is an important meeting, please take notes. There will be a test given by your clients afterward, and failing this test is not an option.

This coaching session comes with a guarantee, and it's ironclad.
Your Part
Attend each team meeting here every month, and just pick up on one or more ideas that you like. Implement it, not because I say so, but because it makes sense to you, and it seems likely to work in your own business. Maybe you've heard the same things before, from your friends, a sub or a supplier. Your gut will tell you two things: it'll take some work on your part, but it'll probably also work for you. Implement at least one idea for at least three months and see if it doesn't put thousands of dollars back into your pocket.
My Part
If it doesn't work or is a waste of time, Ill send a free copy of my upcoming book to your toughest competitor.

Read my articles, as well as the others in this magazine that apply to you, and you'll revolutionize your business. You'll earn a "practical" master's degree in the business of masonry construction, and you'll become a more valuable player on your team.

Now, let's get back to the task at hand.
Know, Know, Know -
Yes, Yes, Yes!
Simple message: know your scope of work; know your plans and specs, know your rights and remedies. That's the beginning of knowing how to ask properly. And here's why: before we can talk about the whole concept of getting paid for extra work, let's understand some definitions and establish some basics.

There will be a test given by your clients afterward, and failing this test is not an option.

What is extra work? Most contractors would answer that it's work that is not a part of their base contract. What's your answer?

Full Contact Project Management says that, at best, that answer is just OK. A better answer is: "extra work is actually work that wasn't included in the bid, is going to be performed, and somebody will pay for it." For the purposes of our class discussion, let's agree that we want to be the payve, not the payor!

Why is this definition important? Because extra work doesn't only mean, for example, the cost of adding a vapor barrier. It needs to include a careful analysis of what's included in the building. Is that what the plans and specs showed? Was there any vapor barrier included? Did the specs say that a vapor barrier "may" be included, or "shall" be included? An important distinction, and we'll come back to that in another class.

At virtually every pre-construction meeting I've ever attended, the subject of change orders is addressed - RFIs, approvals, processing, payment, etc. And this is normally where the owner's representative feels obligated to say something like "But there aren't going to be any change orders, right?" He's nice about it, he smiles big, and everybody laughs. Why? Here's the reality:
* The owner is pressing for no changes.
* The architect is praying for no changes.