Masonry Magazine June 2010 Page. 36

Masonry Magazine June 2010 Page. 36

Masonry Magazine June 2010 Page. 36
BUSINESS BUILDING

By George Hedley

Field Change Memos Work

On the jobsite, your crew hits an underground water line not shown on the plans. With water now spraying over excavated and open footings, should you wait for a signed change order to fix the broken line, or take immediate steps to mitigate the damages?

Why I didn't get changes approved in writing

#1: "I'm too busy right now to get the signature." But never too busy to go to court!

#2: "I trust my customer, he seems fair!" How much work will you have to do to pay for $10,000 in unpaid change orders?

#3: "Don't worry, I'm friends with my customer." Friends sign and pay for change orders, enemies don't.

#4: "We've got to keep the job moving, I'll get it later." When we have no leverage!

#5: "I don't want to rock the boat this early in the job." Training your customer starts at the beginning of the job!

#6: "My customer told me we'll work out all the extras at the end of the job." When they're out of money!

Most construction contracts have language allowing contractors to continue working, fix the problem, and keep the job moving. The key is to inform the general contractor or owner as soon as possible. Always call immediately and follow up with a faxed Field Change Memo by the end of the same day. Your contract allows you a specific amount of time to request more money and time for the extra work.

Field Change Memo

Date: 3/15/05
Project: The Perfect Project

Re: Broken Water Line
Field Item: Today, we hit an unidentified underground waterline while excavating footings along column line C. In order to mitigate the damages the gushing water was causing, we immediately shut off the water main, dug out the wet soil, re-compacted the sub-grade, and re-formed the footings.

Additional Cost: Cost Plus Work to be submitted and approved within 5 days.

Additional Time: 2 extra days

Sincerely, Joe Superintendent

Approved: Mr. Customer

The field memo system is a simple way to get a customer's signature authorizing you to proceed with extra work, and acknowledging you'll agree on a price later. The actual change order can involve many parties including the subcontractor, general contractor, construction manager, architect or engineer, project owner and lender. In a typical situation, the subcontractor submits a change order request. The builder's project manager reviews it and submits a change order request to the owner. The owner has the architect or engineer approve it. And then, if it's valid, the bank must approve it so the progress payment cost breakdown can be processed. Those steps can sometimes take three, six or 12 weeks. The final price of owner requested changes is usually approved prior to starting the extra work. On unwanted extras, most change orders are rarely approved prior to the start of the work.

Charge the right price

Most contracts delineate how to proceed with change orders. There are three standard ways extra work can be performed by your contracts:

* Lump Sum- A fixed price for all extra work required
* Detailed Cost Breakdown - A detailed estimate with backup


Masonry Magazine December 2012 Page. 45
December 2012

WORLD OF CONCRETE

REGISTER NOW; RECEIVE A FREE HAT!
The first 25 people to register this month using source code MCAA will receive a free MCAA Max Hat (valued at $15.00)! The MCAA Max Hat features a 3D MCAA logo embroidered on front with a

Masonry Magazine December 2012 Page. 46
December 2012

Index to Advertisers

AIRPLACO EQUIPMENT
888.349.2950
www.airplace.com
RS #296

KRANDO METAL PRODUCTS, INC.
610.543.4311
www.krando.com
RS #191

REECHCRAFT
888.600.6060
www.reechcraft.com
RS #3

Masonry Magazine December 2012 Page. 47
December 2012

AMERIMIX
MORTARS GROUTS STUCCOS

Why Amerimix Preblended Products?

576

The choice is CLEAR:

Consistency

Labor reduction

Enhanced productivity

ASTM - pretested to ASTM specifications

Masonry Magazine December 2012 Page. 48
December 2012

MASON MIX
Type S Mortar
QUIKRETE
www.quikrete.com
800-282-5828

MASON MIX
Type 5 Mortar
COMMERCIAL GRADE
QUIKRETE

Our mortar mix on Vail's Solaris was so consistent, every bag was like the next. And the next