Question:  What is the tolerance of a CMU wall?  How far out of plumb can a CMU wall be and still be within code?

As everyone should be aware the “code” in question is the “Building Code Requirements and Specification for Masonry Structures” (aka, TMS 402/602). The answer to the question is found in TMS 602: Specification Article 3.3F titled “Site Tolerances”, which gives several construction tolerances.

But before we answer the question regarding plumb walls, we need to go back to Specification Article 1.6C commentary.  This is important enough that we will quote it. “Tolerances listed in Specification Article 3.3F were established to assure structural performance and were not based on aesthetic criteria.”

What this means is that any tolerances given will allow the wall to perform as designed.  Some of these tolerances given may not look pleasing to the architect or owner. They are not meant to! They are for structural performance. 

Now, to answer the question regarding plumb. Article 3.3F.2.b states that we have +/- ¼ inch in 10’-0”, 3/8 inch in 20 feet, and ½ inch maximum tolerance. The symbol +/- means plus or minus not plus and minus. Any wall height beyond 20 feet has a maximum of ½ inch deviation out of plumb. 

Please understand there are other publications that list construction tolerances. A couple of these are BIA Tech Notes 11C and D and NCMA Tek Note 03-8A. Unless they are specifically referenced, they are only guidelines. Also note, there are tolerances listed in the Canadian Masonry Standards.

One thing you must absolutely read are the project specifications.  All projects should have specifications that will follow the layout of a published set of specifications, such as MasterSpec, or they (designers) can write their own. This is where you must read with your very best comprehension.  An architect/engineer (A/E) can design/specify tolerances more stringent than TMS 602. If they do, and the tolerances the A/E specify cannot be met for whatever reason, you MUST notify the A/E immediately.  Notification after the work is complete could mean the wall comes down at your expense.

Currently there is no ASTM Standard that include construction tolerances. There is a proposed Standard on Masonry Workmanship that has been worked on for well over 20 years. One of the major stumbling blocks are tolerances. A single set of tolerances has gotten nowhere. Multi-level tolerances have also been discussed. The general belief is that a specifier will select the highest (precision) level every time while specifying the lowest grade of unit masonry. So, a discussion on tolerances for visual aesthetics will haves to happen another day.

Remember, read your project specifications and understand what they are saying. Just because it is in writing doesn’t make it workable. When in doubt ask questions.

If you have questions regarding a Code or Standard issue send it to MCAA.

Raise the line and come on around the corner!

Masonry Equipment Safety: Meeting New OSHA Standards with Smart Solutions
July 2025

Masonry work, involving cutting, grinding, drilling, and laying stone, brick, or concrete blocks, presents numerous safety hazards—many of which stem from improper equipment use or poor jobsite practices. With evolving Occupational Safety and Health Admin

The STABILA Force Driven by Operations
July 2025

Leadership In today's competitive business landscape, maintaining an efficient, well-organized warehouse is essential for meeting customer demands and ensuring smooth operations. By implementing effective processes and best practices, businesses can achi

MASONRY STRONG Podcast, Episode 24 Recap: Gary Hensley, VP of Sales at Oldcastle Adams
July 2025

On this episode of the MASONRY STRONG Podcast, Gary Hensley joins Justin in Indianapolis to talk about his story within the masonry industry, how he got started, how he's seen it evolve, and where he sees it going. Why the Masonry Industry? Concrete and

The Enduring Power of Structural Masonry
July 2025

Masonry has been holding its ground for millennia — literally. And thanks to the simple brilliance of arching action, it continues to do so with strength, style, and surprising efficiency. In an era of advanced modeling and fast-moving schedules, one time