Case Studies: Restoring the Historic Eads Bridge

Words: Dan KamysMarch 2016

Rehabs and Restorations

By Rick Kerperien Department Manager, Western Specialty Contractors

historic Eads Bridge Western Specialty Contractors – St. Louis Masonry Branch faced a unique set of challenges when asked in early-2015 to restore a brick archway supporting the historic Eads Bridge. The bridge crosses the Mississippi River between St. Louis, Mo., and East St. Louis, Ill. historic Eads BridgeBacked by 100 years of experience and with a little modern ingenuity, Western’s crews were able to restore the 141-year-old archway to its structurally sound, original condition in just a matter of months. The iconic Eads Bridge was the first steel structure bridge of its kind in the United States when it was designed by James B. Eads and opened on July 4, 1874. A significant engineering feat for its time, the historic bridge was in desperate need of rehabilitation from decades of use, repairs and environmental exposure. In May 2012, the Bi-State Development Agency/Metro (BSDA/Metro) launched a monumental Eads Bridge Rehabilitation project, largely funded through $34 million in federal support. That support included $25 million from American Recovery and Reinvestment Act (ARRA) funds. All phases of the project are scheduled to be completed in 2016 and expected to extend the life of the bridge by 50 years. The top deck of the bridge, which supports vehicle and pedestrian travel, is owned by the City of St. Louis. BSDA/Metro owns the superstructure and the lower deck, which is the rail deck that supports the region’s MetroLink light rail system. The multi-faceted restoration project includes replacing support steel, dating from the 1880s; refinishing and repainting the bridge’s superstructure using a rust-inhibiting coating; upgrading the MetroLink light rail system; and restoring a brick archway under the bridge that supports its foundation. historic Eads Bridge St. Louis Bridge Co., a large bridge construction company working throughout the Midwest, hired Western Specialty Contractors  as a subcontractor on the project, based on Western’s expertise in historical masonry restoration. Western’s scope of work focused on restoring the bridge’s brick archway support on the Missouri side, which is located about 100 yards from the waterfront and allows roadway and pedestrian traffic under the bridge. Western was contracted to remove, replace and tuckpoint about 1,256 square feet of deteriorating brick and mortar joints within the archway. Decades of concrete patching and weathering had caused the facing of the archway brick to become dislodged with spalling, creating a hazard for falling debris. Because of the historical significance of the bridge, Western crews were careful to select replacement bricks and mortar that closely matched the original materials used. historic Eads BridgeWork on the project began by removing the concrete patches and damaged brick, and then determining the soundness of the remaining brick and substrate using hammers. Western crews discovered that there was more damaged brick on the project than anticipated, and eventually removed a total of 1,824 square feet of brick and tuckpointed only 469 square feet. One of the challenges that Western’s crews faced on the project included removing and installing brick in the overhead arch, which reaches 30 feet high at its center. Western found a solution to the vertical challenge by using a 40-foot scissor lift and anchoring wood strips to the arch ceiling that would hold the new brick securely in place during installation. Once the brick cured, Western crews removed the wood strips, and then filled in the holes where necessary. Since the Mississippi River is only about 200 feet away from the archway, Western crews were challenged with securing electricity and usable water on the site for mixing all of the mortar they needed, plus cleaning the entire archway. The nearest available usable water source was three blocks away. St. Louis Bridge Co. stepped up to the plate by delivering water in containers to the jobsite for Western’s crews to use. Portable generators, which required additional security protection, provided the electricity needed. The final phase of the project, which involved cleaning the entire archway, began once Western’s crews completed the restoration work. In order to protect the nearby river environment and the historical integrity of the archway, Western crews used water-soluble products applied at a low psi level and collected all of the water runoff. The resulting restoration provides a safe, supportive and historically accurate archway support for generations to utilize and admire into the future.
Australian Bricks vs American Bricks: What 24 Hours of Travel Teaches You About the Trade
June 2026

Bricklaying might not change simply because you cross a state line. It does change when you travel 24 hours to the other side of the world and lay bricks under lights, cameras, and a stopwatch. The fundamentals of the trade are universal. Brick, mortar,

2026 Masonry Foundation Grants Now Open
June 2026

The Masonry Foundation is dedicated to advancing the masonry industry and is accepting grant applications for 2026. Proposals should have national reach and aim to generate substantial progress within the masonry industry. To explore examples of past gra

The “Small Job” Safety Trap: Why Safety Sometimes Fades When the Spotlight Disappears
June 2026

Before I was fortunate enough to lead Malta Dynamics, I spent a couple of years as a traveling salesman for the company. My territory covered the entire country (and some beyond), and in a typical year, I visited more than 100 jobsites across nearly every

Supporting Mental Health in the Workplace
June 2026

As a business owner and leader, taking the mental health of your employees seriously and understanding how it can impact their work is essential. In fact, one in five adults experiences a mental health condition annually. Addressing mental health is more