March 2008: Legal Issues

Words: Dan KamysMarch 2008 Legal Issues

Subcontractors Beware: Bid Conditions Matter

legal-mullinsTimothy HughesBy Timothy R. Hughes and Alison R. Mullins

Subcontractors bidding on projects must thoroughly review and understand the terms of the bid documents. A failure to read and understand the conditions can have incredibly harsh results. A recent decision issued by an intermediate appellate court in New York State had harsh implications for a subcontractor who proceeded with work without having a signed contract. The court ruled that, under the bid documents, the subcontractor was entitled to nothing, despite properly performing significant work.

Not bound until set in stone

In Jordan Panel Systems, Corp. v. Turner Construction Co., the general contractor solicited bids from several subcontractors to design and construct a steel hanger at an airport. The subcontractor submitted a bid to the contractor. During the contract negotiations, the general contractor sent the subcontractor a term sheet.

The term sheet included a provision which stated that, "unless and until [the general contractor] executes this Subcontract, [the general contractor] shall not be bound by any of the terms or conditions herein." The term sheet also included language to the effect that if the general contractor had not signed the subcontract by a certain date, "Šneither [the general contractor] nor the Subcontractor shall have any liability to the other and [the general contractor] shall have no liability to make payments for Work performed by Subcontractor, if any, or for anticipated profits." These two sentences proved damning to the subcontractor.

The subcontractor claimed that a few days after receipt of the term sheet, there was a phone call between the general contractor and the subcontractor. The subcontractor claimed the parties agreed to a subcontract price. During the same phone call, the general contractor informed the subcontractor that they had been awarded the subcontract and directed the subcontractor to begin the design work in order to accommodate the project's fast track schedule. There was a subsequent kick-off meeting including the subcontractor, general contractor and additional parties.

Just two short days after the kick-off meeting, the subcontractor was informed that the general contractor was terminating the subcontractor's involvement in the project. The subcontractor brought suit against the contractor to enforce the contract and to receive payment for work performed. The court rejected all of the subcontractor's claims based on the contract provision above.

The court was unsympathetic to the subcontractor. The court held that, because the general contractor specified in writing that it would not be bound until it had signed the subcontract, the subcontractor could not have reasonably relied on the general contractor's verbal hiring. Further, the court held that, "[The subcontractor] could not have had any reasonable expectation of compensation for the work it performed in the absence of such a signed subcontract." Therefore, the subcontractor recovered nothing for the work it performed.

Implications

Other courts are following the lead of the reasoning of the Jordan Panel Systems case. A federal court applying New Jersey law recently held that the plain language in a subcontractor's bid, where the bid clearly stated that the bid was for information purposes and was not a firm offer, would be enforced. The court's enforcement of the bid's language barred the subcontractor from recovering any damages from the contractor. As a subcontractor, you should expect and plan for strict enforcement of bid terms and conditions, no matter how severe.

Lessons learned

When putting out bids for a job, you should make sure to thoroughly read and understand the terms and conditions of all the bid documents. Most importantly, get everything in writing and have a signed contract before proceeding with work. As the above cases demonstrate, lack of a signed written agreement can permanently kill your ability to get paid.
Timothy R. Hughes, Esq. is the principal of the Virginia law firm of Hughes & Associates, P.L.L.C, www.hughesnassociates.com. He may be reached at tim@hughesnassociates.com. Alison R. Mullins, Esq. is an associate with Hughes & Associates. She may be reached at alison@hughesnassociates.com or 703-671-8200. This article is not intended to provide specific legal advice, but instead as general commentary regarding legal matters. You should consult with an attorney regarding your legal issues, as the advice you may receive will depend upon your facts and the laws of your jurisdiction.      
Laying the Foundation for the Future: Workforce Development at the Arizona Masonry Council
July 2026

For generations, masonry has been built on a simple but powerful principle: knowledge passed from one set of hands to the next. In Arizona, the Arizona Masonry Council (AMC) is working to ensure that tradition continues by investing in one of the industr

What Mason Contractors Don't Know Is Costing Them Money
July 2026

Most mason contractors can tell you exactly what a job should cost before it starts. Bid labor hours, material takeoffs, and crew rates per square foot. The numbers are on paper, and they look right. What most can't tell you is whether those numbers held

Preserving Masonry Aesthetics with Concealed Lintel Systems
July 2026

Masonry has long been valued for its ability to create buildings with character, permanence, and visual appeal. Features such as arches, deep reveals, corbelling, and decorative brickwork continue to be popular design elements in modern architecture. Howe

The Sync Up: Aligning Schedule, Labor, and Logistics in Masonry
July 2026

A masonry contractor is only as good as the crew standing on the staging. You can source the highest-grade block, line up the perfect mix, and have every submittal approved weeks in advance, but production ultimately depends on the stamina, skill, and phy