Mason Contractors: Stop Giving Money Away

Words: Dan KamysMason Contractors: Stop Giving Money Away

By George Hedley

Every dollar counts, and every penny wasted is precious. Losing small change on your construction projects can add up to thousands of dollars at the end of the year. So, what are you to do?

Maximizing profit must be a top priority, right along with getting your projects completed on-time. Setting aside a little time to focus on increasing your net profit will boost your bottom line and allow you to make a lot more money.

When you’re too busy working on the jobs, scheduling crews, or carrying out work tasks, you don’t take or have enough time to focus on finances, financial tools, and strategies that can help you hit your goals. Consider implementing these two proven strategies to maximize your bottom line and grow your bank balance.

Accurate general conditions

General conditions in construction include the onsite administration, supervision, temporary facilities, temporary protection, and soft costs required to get your projects built. Estimating accurate general conditions for projects can be a simple task, when the estimator is accountable to get it right.

Most estimators use unit prices that are rarely checked against the actual final job costs. For example, creating a budget for temporary toilets seems easy. An eight-month job should cost 8 x $100 per month = $800. But, when the field superintendent sees there are 40 men on the job, more than one toilet and more than one servicing a week are required. This might increase the actual job cost by as much as $200 per month. These extra costs will add up to lots of lost cash.

The estimator’s No. 1 job is to calculate an accurate estimate of what it will cost to build each project. After every job, he must look at the actual job costs to see if he miscalculated or under-estimated any of the project line items. Before pricing every job, the estimator should get with the project manager, field superintendent or foreman to determine what will be required to run the project he currently is bidding.

Take a hard look to determine if you are charging the right price for:

??       Project manager, superintendent and their vehicles

??       Project photos, sign, as-built drawings, etc.

??       Temporary facilities, trailers, toilets, sanitation, etc.

??       Temporary utilities, electricity, power poles, water, phones, etc.

??       Temporary fencing, gates, barricades, site lighting, heating, etc.

??       Safety, first aid, shoring, access roads, security guards, etc.

??       Water quality control, dust control, etc.

??       Trash, cleanup, window washing, final punch list, etc.

Charge for all the changes on change orders

Change orders are written documents amending the original contract agreement between parties memorializing an additional or changed scope, price, time, schedule, terms or work item on a construction project. Most often, they require additional money for the additional work required by the change.

As contractors, if you had $10 for every extra work item your company, project manager, field superintendent or foreman did without a signed change order before the work was performed, could you have retired several years ago? When your customer asks for extra work, why is it so hard to get it in writing?

Everyone knows the contract requires signatures on change orders prior to starting extra work. But when you postpone getting a formal approval for extra work until days, weeks or months after the event occurred, you have no leverage with your customer. Your customer is in a great position to offer a reduced, discounted price with you; change his mind; or decide the additional work wasn’t really extra and should have been included in the original contract.

To avoid this problem, present a complete cost breakdown for every proposed change order your customer requests in advance of starting the work. Use a standardized format, cost template, and rate sheet to assure you include all actual costs. Every time extra work is performed, the followings costs occur:

??               Project management to process the paperwork

??               Supervision to supervise the work

??               Accounting to process the payment

??               General condition costs as the job will take longer:

   -        Trailer, toilets, water and utilities

   -        Power and power poles

   -        Trucks and equipment

   -        Small tools, ladders, bins, etc.

   -        Small items, nuts, bolts, hardware, etc.

   -        Temporary facilities, fencing, protection, barricades, etc.

??       Liability insurance

??       Overhead and profit

Don’t shortchange your company by not asking for everything you deserve. I see most change order requests presented as labor, materials and hard costs, plus a markup without extra required soft costs for the many items listed above. If your company does $5 million in annual sales, of which $250,000 is performed as change orders or on a cost-plus basis, not charging for everything you spend can cost you as much as $25,000 or more per year in lost revenue or net profit for things that you actually had to pay for.

Making money is not easy in construction. Look for every advantage you have to boost your net profit margin. Take the time to implement these tools and send me an email of the other tools you use to increase your net numbers. Email GH@HardhatPresentations.com to get your copy of “Project Management Forms For Contractors.”



George Hedley works with contractors, entrepreneurs and business owners to build profitable growing companies. As a construction company owner, he has built more than 500 projects valued at more than $500 million and was name Construction Entrepreneur of the Year. He is a leading construction business expert, professional business coach, popular professional speaker, best-selling author of “Get Your Business To Work!” and presenter at his Hardhat BIZSCHOOL online university. To find out how George can help your company, signup for his e-newsletter, be part of a group BIZCOACH program, or join a peer mastermind BIZGROUP, visit his websites: www.HardhatPresentations.com or www.HardhatBIZSCHOOL.com, or email GH@HardhatPresentations.com.

George Hedley, HARDHAT Presentations 800-851-8553

Is Contact with Wet Mortar or Grout Dangerous?
April 2026

In the world of masonry, few materials are as common as mortar and grout. Whether you are laying brick, concrete masonry units (CMU), or pouring grout into masonry walls, wet cement and mortar are constant companions. However, beneath their utility lies a

The Importance of Instructor Support
April 2026

Whether you are a new or veteran masonry instructor, we all need support throughout our careers. We can never stop learning, and keeping up with ever-changing technology, materials, and installation techniques can be overwhelming alongside the everyday pr

Vibing Masonry #11: Innovative Concrete Masonry Technologies in Healthcare Design
April 2026

In the high-stakes environment of healthcare design, every material choice is a clinical decision. Architects, engineers, and facility administrators are tasked with creating spaces that are not only resilient and code-compliant but also conducive to heal

Why Termination Bars Still Matter: A Practical Look at Long‑Term Flashing Performance
April 2026

In recent discussions across the masonry industry, I have heard termination bars described as “old school.” The implication is that with modern materials, primerless peel-and-stick flashings, advanced sealants, and structural insulated sheathing, mechanic