December 2008: Legal Issues

Words: Dan KamysDecember 2008 Legal Issues

Notice Me

???? Information about the Masonry Industry ???? Information about the Masonry Industry
By Timothy R. Hughes and Alison R. Mullins

In the terms and conditions of many construction contracts, giving written notice of a possible legal claim for damages is a prerequisite for filing suit later. Lack of proper and timely notice may completely negate a valid claim. A recent decision issued by a Virginia Circuit Court may remove some of the fear from such defenses by adding some flexibility and practicality to the often-rigid written notice requirements in contracts. The court ruled that, because the defendants had actual notice, lack of written notice was not a valid defense.

Lack of written notice, not an excuse In AMEC Civil, LLC v. Commonwealth of Virginia, the Virginia Department of Transportation (VDOT) awarded a contract for the construction of about four miles of roadway and 11 bridges to AMEC Civil, LLC, as the contractor. Differing site conditions arose throughout performance of the contract. Despite attempts to resolve issues surrounding the differing site conditions, about six years into the contract, the contractor filed a lawsuit against the VDOT alleging breach of contract.

The VDOT argued lack of timely notice barred the contractor's claims. The contract between the VDOT and the contractor included a provision stating, "Early or prior knowledge by the department of an existing or impending claim for damages could alter the plans, scheduling or other action of the department, or result in mitigation or elimination of the effect of the act objected to by the contractor." The provision continued to require the contractor to provide written notice "describing the act of omission or commission by the department or its agents that allegedly caused the damages."

The VDOT bolstered their argument by pointing to statutes requiring notice of claims on state highway projects. The court agreed that the applicable state statutes required written notice. The court cited and agreed, however, with the Supreme Court of Virginia's holding that, as long as a required act was performed, even if it is not within the statutory time or mode, it will be adequate if the substantial purpose of the statute is accomplished.

The contractor argued the VDOT had actual notice of the claims and, thus, substantially complied with the purpose of both the contractual and statutory provisions for written notice. The VDOT never argued that they lacked knowledge of the contractor's claims. In fact, the court found that the evidence was clear that the VDOT and the contractor communicated regarding the contractor's claims during the performance of the contract work. These communications between the parties included meetings, written meeting minutes and memorandum of issues discussed. Further, the court found that the "VDOT did not suffer any prejudice from receiving actual notice as opposed to written notice."

In making the ruling, the court focused on the underlying purpose of the contract terms and statutory notice. The court found that the documentation of discussions, meeting minutes and claims demonstrated that the VDOT was aware of the contractor's claims. As such, actual notice satisfied the underlying contract and statutory purposes. Therefore, the contractor's claims were not barred by failure to provide written notice to the VDOT.

Implications Best practices dictate strict compliance with all notice provisions whenever possible. Actual circumstances and communications may be enough to demonstrate notice. Context matters greatly as the law from state to state may vary, as may facts from project to project. This is an arena where more is most definitely better. Conclusion Knowing your obligations can help you to protect and preserve your legal rights, including enforcement of contractual payment provisions. Failing to send proper and timely notice may bar your claim. While actual notice may be a way around the written notice requirement, as a contractor or subcontractor you should expect and plan for strict enforcement of contractual and statutory requirements for notice of claims and properly preserve your rights.

Return to Table of Contents
Natural Stone Ordering: Details Matter Before the Job Starts
October 2026

A lot of problems on a stone job can be traced back to the order. I’m on the supplier side, so I see it regularly. A mason can do everything right in the field and still end up fighting a job because the wrong material was ordered, quantities were off, c

Dust Mitigation in Masonry: Practical Strategies for Safer Job Sites
October 2026

Every day, masonry professionals cut block, grind mortar joints, core drill, mix dry materials, and demolish existing structures. These tasks are fundamental to the trade, but they also generate dust. While dust may seem like an unavoidable part of the jo

What Does That Marking Actually Mean?: Understanding the Standards Behind Your PPE
October 2026

Walk onto almost any masonry project, and you will see a variety of markings on personal protective equipment: Z87+, Type I, Type II, Class E, ANSI, and others. We recognize many of these markings and know they are important, but understanding exactly wha

TERRA Footwear Renews as a Silver Partner in 2027
October 2026

The Mason Contractors Association of America (MCAA) is pleased to share that TERRA Footwear will renew as a Silver Partner in the 2027 Masonry Alliance Program.