December 2008: Legal Issues

Words: Dan KamysDecember 2008 Legal Issues

Notice Me

???? Information about the Masonry Industry ???? Information about the Masonry Industry
By Timothy R. Hughes and Alison R. Mullins

In the terms and conditions of many construction contracts, giving written notice of a possible legal claim for damages is a prerequisite for filing suit later. Lack of proper and timely notice may completely negate a valid claim. A recent decision issued by a Virginia Circuit Court may remove some of the fear from such defenses by adding some flexibility and practicality to the often-rigid written notice requirements in contracts. The court ruled that, because the defendants had actual notice, lack of written notice was not a valid defense.

Lack of written notice, not an excuse In AMEC Civil, LLC v. Commonwealth of Virginia, the Virginia Department of Transportation (VDOT) awarded a contract for the construction of about four miles of roadway and 11 bridges to AMEC Civil, LLC, as the contractor. Differing site conditions arose throughout performance of the contract. Despite attempts to resolve issues surrounding the differing site conditions, about six years into the contract, the contractor filed a lawsuit against the VDOT alleging breach of contract.

The VDOT argued lack of timely notice barred the contractor's claims. The contract between the VDOT and the contractor included a provision stating, "Early or prior knowledge by the department of an existing or impending claim for damages could alter the plans, scheduling or other action of the department, or result in mitigation or elimination of the effect of the act objected to by the contractor." The provision continued to require the contractor to provide written notice "describing the act of omission or commission by the department or its agents that allegedly caused the damages."

The VDOT bolstered their argument by pointing to statutes requiring notice of claims on state highway projects. The court agreed that the applicable state statutes required written notice. The court cited and agreed, however, with the Supreme Court of Virginia's holding that, as long as a required act was performed, even if it is not within the statutory time or mode, it will be adequate if the substantial purpose of the statute is accomplished.

The contractor argued the VDOT had actual notice of the claims and, thus, substantially complied with the purpose of both the contractual and statutory provisions for written notice. The VDOT never argued that they lacked knowledge of the contractor's claims. In fact, the court found that the evidence was clear that the VDOT and the contractor communicated regarding the contractor's claims during the performance of the contract work. These communications between the parties included meetings, written meeting minutes and memorandum of issues discussed. Further, the court found that the "VDOT did not suffer any prejudice from receiving actual notice as opposed to written notice."

In making the ruling, the court focused on the underlying purpose of the contract terms and statutory notice. The court found that the documentation of discussions, meeting minutes and claims demonstrated that the VDOT was aware of the contractor's claims. As such, actual notice satisfied the underlying contract and statutory purposes. Therefore, the contractor's claims were not barred by failure to provide written notice to the VDOT.

Implications Best practices dictate strict compliance with all notice provisions whenever possible. Actual circumstances and communications may be enough to demonstrate notice. Context matters greatly as the law from state to state may vary, as may facts from project to project. This is an arena where more is most definitely better. Conclusion Knowing your obligations can help you to protect and preserve your legal rights, including enforcement of contractual payment provisions. Failing to send proper and timely notice may bar your claim. While actual notice may be a way around the written notice requirement, as a contractor or subcontractor you should expect and plan for strict enforcement of contractual and statutory requirements for notice of claims and properly preserve your rights.

Return to Table of Contents
Designing for Performance: Key Considerations for Efficient, Durable Masonry Projects
August 2026

A successful masonry project starts well before the first stone is set. The craftsmanship on site matters, of course, but many of the decisions that shape the final result are made much earlier—during design, detailing, and material selection. Those choic

Change Orders: Standard Operating Procedure
August 2026

In masonry construction, change orders are not occasional events; they are guaranteed. Drawings do not always match field conditions, specifications can conflict, and real-world construction has a way of exposing gaps in design. At DRP Masonry, we operat

RFIs: Clarity, Communication and... Hierarchy?
August 2026

In construction, any project starts with drawings. Plans. Schedules. Specifications. Whether we're talking about new construction, additions, or restoration, there is a plan, there is design intent, and a way every piece of a project needs to fit together

Zero Laydown: Navigating the Logistics of Tight Urban Job Sites
August 2026

In modern commercial construction, spatial real estate has become just as valuable as the materials themselves. The industry shift toward high-density, urban projects means that the sprawling job sites of the past have been replaced by tight footprints wh