December 2008: Legal Issues

Words: Dan KamysDecember 2008 Legal Issues

Notice Me

???? Information about the Masonry Industry ???? Information about the Masonry Industry
By Timothy R. Hughes and Alison R. Mullins

In the terms and conditions of many construction contracts, giving written notice of a possible legal claim for damages is a prerequisite for filing suit later. Lack of proper and timely notice may completely negate a valid claim. A recent decision issued by a Virginia Circuit Court may remove some of the fear from such defenses by adding some flexibility and practicality to the often-rigid written notice requirements in contracts. The court ruled that, because the defendants had actual notice, lack of written notice was not a valid defense.

Lack of written notice, not an excuse In AMEC Civil, LLC v. Commonwealth of Virginia, the Virginia Department of Transportation (VDOT) awarded a contract for the construction of about four miles of roadway and 11 bridges to AMEC Civil, LLC, as the contractor. Differing site conditions arose throughout performance of the contract. Despite attempts to resolve issues surrounding the differing site conditions, about six years into the contract, the contractor filed a lawsuit against the VDOT alleging breach of contract.

The VDOT argued lack of timely notice barred the contractor's claims. The contract between the VDOT and the contractor included a provision stating, "Early or prior knowledge by the department of an existing or impending claim for damages could alter the plans, scheduling or other action of the department, or result in mitigation or elimination of the effect of the act objected to by the contractor." The provision continued to require the contractor to provide written notice "describing the act of omission or commission by the department or its agents that allegedly caused the damages."

The VDOT bolstered their argument by pointing to statutes requiring notice of claims on state highway projects. The court agreed that the applicable state statutes required written notice. The court cited and agreed, however, with the Supreme Court of Virginia's holding that, as long as a required act was performed, even if it is not within the statutory time or mode, it will be adequate if the substantial purpose of the statute is accomplished.

The contractor argued the VDOT had actual notice of the claims and, thus, substantially complied with the purpose of both the contractual and statutory provisions for written notice. The VDOT never argued that they lacked knowledge of the contractor's claims. In fact, the court found that the evidence was clear that the VDOT and the contractor communicated regarding the contractor's claims during the performance of the contract work. These communications between the parties included meetings, written meeting minutes and memorandum of issues discussed. Further, the court found that the "VDOT did not suffer any prejudice from receiving actual notice as opposed to written notice."

In making the ruling, the court focused on the underlying purpose of the contract terms and statutory notice. The court found that the documentation of discussions, meeting minutes and claims demonstrated that the VDOT was aware of the contractor's claims. As such, actual notice satisfied the underlying contract and statutory purposes. Therefore, the contractor's claims were not barred by failure to provide written notice to the VDOT.

Implications Best practices dictate strict compliance with all notice provisions whenever possible. Actual circumstances and communications may be enough to demonstrate notice. Context matters greatly as the law from state to state may vary, as may facts from project to project. This is an arena where more is most definitely better. Conclusion Knowing your obligations can help you to protect and preserve your legal rights, including enforcement of contractual payment provisions. Failing to send proper and timely notice may bar your claim. While actual notice may be a way around the written notice requirement, as a contractor or subcontractor you should expect and plan for strict enforcement of contractual and statutory requirements for notice of claims and properly preserve your rights.

Return to Table of Contents
MASONRY STRONG Podcast, Episode 36 Recap: Kim Spahn, CEO of the Concrete Masonry Checkoff
January 2026

On this episode of the MASONRY STRONG Podcast, Justin got to sit down for a conversation with Kim Spahn to talk about the Concrete Masonry Checkoff, how Kim first got involved in this industry, and much more.

From Day One to Long-Term Success: Onboarding Strategies for Contractors
January 2026

The construction industry is facing one of its toughest challenges in decades. Companies are struggling to find enough skilled workers while competing to keep the ones they have. At the same time, projects are becoming more complex, deadlines are tighter,

Finding the Right PPE for Your Work
January 2026

When it comes to PPE, one thing’s for sure: safety isn’t one size fits all. The work you’re doing, where you’re doing it, and even what time of year it is, can all make a big difference in what gear actually works. Price, comfort, and job performance all

Back Injuries: The Real Cost and How to Prevent Them
January 2026

The mention of back injuries makes mason contractors cringe, and for good reason. Masons lift heavy objects every day, all day long. When a person sustains a back injury, it is serious. It affects every part of their life, from their ability to perform wo