December 2008: Legal Issues

Words: Dan KamysDecember 2008 Legal Issues

Notice Me

???? Information about the Masonry Industry ???? Information about the Masonry Industry
By Timothy R. Hughes and Alison R. Mullins

In the terms and conditions of many construction contracts, giving written notice of a possible legal claim for damages is a prerequisite for filing suit later. Lack of proper and timely notice may completely negate a valid claim. A recent decision issued by a Virginia Circuit Court may remove some of the fear from such defenses by adding some flexibility and practicality to the often-rigid written notice requirements in contracts. The court ruled that, because the defendants had actual notice, lack of written notice was not a valid defense.

Lack of written notice, not an excuse In AMEC Civil, LLC v. Commonwealth of Virginia, the Virginia Department of Transportation (VDOT) awarded a contract for the construction of about four miles of roadway and 11 bridges to AMEC Civil, LLC, as the contractor. Differing site conditions arose throughout performance of the contract. Despite attempts to resolve issues surrounding the differing site conditions, about six years into the contract, the contractor filed a lawsuit against the VDOT alleging breach of contract.

The VDOT argued lack of timely notice barred the contractor's claims. The contract between the VDOT and the contractor included a provision stating, "Early or prior knowledge by the department of an existing or impending claim for damages could alter the plans, scheduling or other action of the department, or result in mitigation or elimination of the effect of the act objected to by the contractor." The provision continued to require the contractor to provide written notice "describing the act of omission or commission by the department or its agents that allegedly caused the damages."

The VDOT bolstered their argument by pointing to statutes requiring notice of claims on state highway projects. The court agreed that the applicable state statutes required written notice. The court cited and agreed, however, with the Supreme Court of Virginia's holding that, as long as a required act was performed, even if it is not within the statutory time or mode, it will be adequate if the substantial purpose of the statute is accomplished.

The contractor argued the VDOT had actual notice of the claims and, thus, substantially complied with the purpose of both the contractual and statutory provisions for written notice. The VDOT never argued that they lacked knowledge of the contractor's claims. In fact, the court found that the evidence was clear that the VDOT and the contractor communicated regarding the contractor's claims during the performance of the contract work. These communications between the parties included meetings, written meeting minutes and memorandum of issues discussed. Further, the court found that the "VDOT did not suffer any prejudice from receiving actual notice as opposed to written notice."

In making the ruling, the court focused on the underlying purpose of the contract terms and statutory notice. The court found that the documentation of discussions, meeting minutes and claims demonstrated that the VDOT was aware of the contractor's claims. As such, actual notice satisfied the underlying contract and statutory purposes. Therefore, the contractor's claims were not barred by failure to provide written notice to the VDOT.

Implications Best practices dictate strict compliance with all notice provisions whenever possible. Actual circumstances and communications may be enough to demonstrate notice. Context matters greatly as the law from state to state may vary, as may facts from project to project. This is an arena where more is most definitely better. Conclusion Knowing your obligations can help you to protect and preserve your legal rights, including enforcement of contractual payment provisions. Failing to send proper and timely notice may bar your claim. While actual notice may be a way around the written notice requirement, as a contractor or subcontractor you should expect and plan for strict enforcement of contractual and statutory requirements for notice of claims and properly preserve your rights.

Return to Table of Contents
Bonding with Masonry 2024: Q3

This issue’s questions come from a Mason Contractor, an Architect, and an Engineer.  What questions do you have? Send them to info@masonrymagazine.com, attention Technical Talk.   Q.  A Mason Contractor writes that they have a project to install a concret

About: Featured
How Technology Can Help Increase Efficiency Within Your Masonry Company

Masonry, a craft as old as civilization itself. From the Pyramids of Egypt to the Great Wall of China, we've been stacking bricks with a precision that would make any Lego master jealous. But let's face it, while the techniques might be ancient, the chall

Energy Efficient Shelf Angles in Modern Construction

The conversation around energy efficiency in buildings is multifaceted, requiring a holistic approach to achieve high-performance building envelopes. One often overlooked component in this discussion is the role of shelf angles used in supporting masonry

Masonry in the Media - Highclere Castle, Chatsworth House and More!

Located in Hampshire, England, Highclere Castle has gone through three iterations from its beginnings in the medieval era to today. Ownership of the estate’s land can be traced back to 749 A.D.

About: Featured