Have you noticed me lately?

Words: George HedleyConstruction is a difficult business, with lots of moving parts. On every project, there are 5,947 chances for things to go wrong. Contractors find themselves at the mercy of project plans, changes, payments, scheduling, weather, labor, equipment, materials and deliveries. So much is out of their control. At the end of every job (when it’s too late to do much about it), the bottom-line reality of what the project manager, superintendent or foreman has or, more typically, has not done, to manage the contract properly becomes apparent. Not paying attention to key contract clauses about notice, documentation and change order procedures is a sure way to watch your profit dwindle.

Contracting is about contracts

Most contractors don’t like paperwork. But, unfortunately, contracting is about contracts, and contracts are paperwork. As much as 50 percent of all profits made or lost on construction projects can be as a result of managing the contract properly. The contract or subcontract defines how you must do business with your customer. Too many contractors and subcontractors sign pre-prepared five-, 10-, 15- or 20-page contracts without reading them or having their attorney review them, or without understanding the specific contractual requirements.

Did you notice?

One of the first things to look for when reviewing your contract is: What requires notice? “Notice” is proper notification to your customer about a change, conflict, incident, omission or problem, within a specified number of days, and in a specified format (usually in writing). Before you start a project, review the contract and prepare a chart listing items that require proper notice.

WIN with no VAs

In the construction business, you must use the slogan: WIN = Write It Now. Phone calls, meetings or meeting minutes are not proper notice or documentation. Another saying we enforce is no VAs = no Verbal Agreements. Verbal agreements aren’t worth the paper they’re written on.

Be complete

Assembling all documentation, paperwork, change order requests, notices and information required by your contract often seems overwhelming. But once you get in the habit of following the contract, it becomes easy and a normal part of your construction routine. In order to get everything you deserve while building a project for your customer, you must be timely in your requests. Missing the notice time requirements may result in a loss of your right to collect for things out of your scope of work or control. When documenting items, take a little extra time and be complete in your description of the event.

By not documenting conflicts or changes in a timely and complete manner, contractors inadvertently shift more responsibility onto their own shoulders and can lose the right to collect. Providing proper notice starts at the beginning of every project. Meet with your customer to discuss the contract terms and what it requires. Review and agree on the project notice and documentation required for every conflict or change. And then, be ready to follow the contract.
Designing for Performance: Key Considerations for Efficient, Durable Masonry Projects
August 2026

A successful masonry project starts well before the first stone is set. The craftsmanship on site matters, of course, but many of the decisions that shape the final result are made much earlier—during design, detailing, and material selection. Those choic

Change Orders: Standard Operating Procedure
August 2026

In masonry construction, change orders are not occasional events; they are guaranteed. Drawings do not always match field conditions, specifications can conflict, and real-world construction has a way of exposing gaps in design. At DRP Masonry, we operat

RFIs: Clarity, Communication and... Hierarchy?
August 2026

In construction, any project starts with drawings. Plans. Schedules. Specifications. Whether we're talking about new construction, additions, or restoration, there is a plan, there is design intent, and a way every piece of a project needs to fit together

Zero Laydown: Navigating the Logistics of Tight Urban Job Sites
August 2026

In modern commercial construction, spatial real estate has become just as valuable as the materials themselves. The industry shift toward high-density, urban projects means that the sprawling job sites of the past have been replaced by tight footprints wh