Have you noticed me lately?

Words: George HedleyConstruction is a difficult business, with lots of moving parts. On every project, there are 5,947 chances for things to go wrong. Contractors find themselves at the mercy of project plans, changes, payments, scheduling, weather, labor, equipment, materials and deliveries. So much is out of their control. At the end of every job (when it’s too late to do much about it), the bottom-line reality of what the project manager, superintendent or foreman has or, more typically, has not done, to manage the contract properly becomes apparent. Not paying attention to key contract clauses about notice, documentation and change order procedures is a sure way to watch your profit dwindle.

Contracting is about contracts

Most contractors don’t like paperwork. But, unfortunately, contracting is about contracts, and contracts are paperwork. As much as 50 percent of all profits made or lost on construction projects can be as a result of managing the contract properly. The contract or subcontract defines how you must do business with your customer. Too many contractors and subcontractors sign pre-prepared five-, 10-, 15- or 20-page contracts without reading them or having their attorney review them, or without understanding the specific contractual requirements.

Did you notice?

One of the first things to look for when reviewing your contract is: What requires notice? “Notice” is proper notification to your customer about a change, conflict, incident, omission or problem, within a specified number of days, and in a specified format (usually in writing). Before you start a project, review the contract and prepare a chart listing items that require proper notice.

WIN with no VAs

In the construction business, you must use the slogan: WIN = Write It Now. Phone calls, meetings or meeting minutes are not proper notice or documentation. Another saying we enforce is no VAs = no Verbal Agreements. Verbal agreements aren’t worth the paper they’re written on.

Be complete

Assembling all documentation, paperwork, change order requests, notices and information required by your contract often seems overwhelming. But once you get in the habit of following the contract, it becomes easy and a normal part of your construction routine. In order to get everything you deserve while building a project for your customer, you must be timely in your requests. Missing the notice time requirements may result in a loss of your right to collect for things out of your scope of work or control. When documenting items, take a little extra time and be complete in your description of the event.

By not documenting conflicts or changes in a timely and complete manner, contractors inadvertently shift more responsibility onto their own shoulders and can lose the right to collect. Providing proper notice starts at the beginning of every project. Meet with your customer to discuss the contract terms and what it requires. Review and agree on the project notice and documentation required for every conflict or change. And then, be ready to follow the contract.
MASONRY MADNESS®: Celebrating Skill, Speed, and the Next Generation of Masons
January 2026

Every January, Las Vegas becomes the heartbeat of the construction industry as thousands of professionals from across the country gather for the World of Concrete Convention. Among the countless exhibits, product showcases, and networking opportunities, o

STABILA Elevates Craftsmanship Supporting SPEC MIX 500 and World of Concrete
January 2026

In the mason’s industry, where the line between “good enough” and “built to last” is often measured by how good the tools are, it’s when craftsmen are proud to hold a STABILA tool. Precision isn’t a luxury; it’s the quiet backbone of every wall, brick, an

GEN NXT: Austin Cataldi
January 2026

This month, the MCAA had a conversation with 19-year-old Austin Cataldi, a dedicated young professional whose path to masonry was shaped by family ties and a hands-on spirit. His journey is one of finding artistic expression in the same materials he works

Outreach Outlook: Launching Into 2026 With Purpose, Innovation, and National Momentum
January 2026

Happy New Year! As classrooms reopen and a new semester begins across the country, the MCAA Outreach & Education Division is entering 2026 with renewed purpose and a clear focus. There is a unique energy that comes with the start of a new year. It is a ti