June 2010: Business Building

Words: George Hedley

altBusiness Building

On the jobsite, your crew hits an underground water line not shown on the plans. With water now spraying over excavated and open footings, should you wait for a signed change order to fix the broken line, or take immediate steps to mitigate the damages?

Why I didn’t get changes approved in writing

#1: “I’m too busy right now to get the signature.” But never too busy to go to court!

#2: “I trust my customer, he seems fair!” How much work will you have to do to pay for $10,000 in unpaid change orders?

#3: “Don’t worry, I’m friends with my customer.” Friends sign and pay for change orders, enemies don’t.

#4: “We’ve got to keep the job moving, I’ll get it later.” When we have no leverage!

#5: “I don’t want to rock the boat this early in the job.” Training your customer starts at the beginning of the job!

#6: “My customer told me we’ll work out all the extras at the end of the job.” When they’re out of money!

Most construction contracts have language allowing contractors to continue working, fix the problem, and keep the job moving. The key is to inform the general contractor or owner as soon as possible. Always call immediately and follow up with a faxed Field Change Memo by the end of the same day. Your contract allows you a specific amount of time to request more money and time for the extra work.

Field Change Memo Date: 3/15/05 Project: The Perfect Project

Re: Broken Water Line Field Item: Today, we hit an unidentified underground waterline while excavating footings along column line C. In order to mitigate the damages the gushing water was causing, we immediately shut off the water main, dug out the wet soil, re-compacted the sub-grade, and re-formed the footings.

Additional Cost: Cost Plus Work to be submitted and approved within 5 days.

Additional Time: 2 extra days

Sincerely, Joe Superintendent Approved: Mr. Customer The field memo system is a simple way to get a customer’s signature authorizing you to proceed with extra work, and acknowledging you’ll agree on a price later. The actual change order can involve many parties including the subcontractor, general contractor, construction manager, architect or engineer, project owner and lender. In a typical situation, the subcontractor submits a change order request. The builder’s project manager reviews it and submits a change order request to the owner. The owner has the architect or engineer approve it. And then, if it’s valid, the bank must approve it so the progress payment cost breakdown can be processed. Those steps can sometimes take three, six or 12 weeks. The final price of owner requested changes is usually approved prior to starting the extra work. On unwanted extras, most change orders are rarely approved prior to the start of the work.

Charge the right price Most contracts delineate how to proceed with change orders. There are three standard ways extra work can be performed by your contracts:

  • Lump Sum - A fixed price for all extra work required
  • Detailed Cost Breakdown - A detailed estimate with backup
  • Cost Plus - Actual costs of the work plus markup

The owner or contractor can require the subcontractor to perform the work lump sum” or fixed price for extra work agreed on prior to starting the work. With a detailed cost breakdown approach, the subcontractor can be required to present the detailed estimate with backup. If the general contractor or owner isn’t satisfied with either the lump sum quote or the detailed cost breakdown price, he can usually force the subcontractor to perform the work on a cost-plus basis.

Many contractors only like to work on a lump sum basis. I’ve been in business a long time, and I know what things should cost. If a subcontractor forwards an extra charge to me in the amount of $750 for a $200 item, and I submit the bill to my customer for approval, my customer will think I’m either trying to gouge him, or I don’t know what things cost. I then have to go back to my subcontractor and tell him to give me a fair price. I now don’t trust my subcontractor, and he doesn’t like dealing with me. When a lump sum estimate is rejected, negotiating over price ensues using the detailed cost breakdown method. Agreements begin and enemies are made at this level. Charge the right price the first time!

Extra work takes extra time In every change order request, always include additional time required to perform the work, even if it doesn’t affect the critical path of the project. No exceptions!

Get paid for what you do by putting it in writing, every time. Start using this Field Change Memo system and you’ll improve your collection ratio.


About: Business Building
The Science of a Straight Line: Why Masonry’s Smallest Decisions Make the Biggest Differences
September 2026

There is a unique phenomenon in construction: the human eye can spot an out-of-plumb wall from 50 yards away across a crowded job site. We might not always be able to explain the exact mathematical deviation without a laser level, but our brains instantly

The Utah Masonry Council's Masonry Education Day
September 2026

The 2026 Masonry Education Day at Interstate Brick in West Jordan is bringing together members of Utah’s architecture, engineering, and construction community for a day focused on education, technical understanding, and workforce development. The event r

MCAA Upstate New York: Regaining Market Share Through Education
September 2026

The Upstate New York chapter of the MCAA was established in 2014 by a dedicated group of both union and non-union masonry contractors, producers, and suppliers who shared concerns about the declining use of masonry. T

GEN NXT: Luis Sontay
September 2026

For this month, the MCAA got to sit down with aspiring mason Luis Sontay. From taking an interest in masonry as a kid to placing 1st in a postsecondary competition, Luis’ dedication and passion for the trade is clear. Luis describes his early passion fo